Three Provinces, Three Rulebooks: Canada Fractures on AI Data Centres
Alberta's Bill 42 would push data-centre cooling water near zero and protect 14 million acres of farmland, as Ontario weighs grid-access tests and Manitoba doubles down on levies.

By Grace Kim
Alberta introduced legislation on Wednesday, November 18 that would force large AI data centres at least 600 metres from homes, off prime farmland and onto their own electricity bills — while Ontario and Manitoba chart sharply different paths on the same problem.
Bill 42, the Energy, Environment and Utilities Statutes Amendment Act, 2026, targets facilities drawing at least 10 megawatts. That threshold matters when you consider scale: a facility running 100 megawatts continuously consumes roughly 876 million kilowatt-hours per year.
Technology and Innovation Minister Nate Glubish said the bill responds to what residents asked for. "Albertans told us what matters most: their communities, farmland and water. We listened," Glubish said in the government's announcement.
What does Bill 42 actually restrict?
The Alberta package stacks four core requirements onto any data centre above 10 MW:
- A general 600-metre setback from the nearest home, with municipalities allowed to set alternative setbacks where local planning supports compatible development
- Restrictions on Class 1 and Class 2 farmland — about 14 million acres — plus Class 3 land in municipalities lacking higher-quality agricultural land, and a ban on irrigated land
- A provincewide standard pushing cooling-water consumption close to zero (evaporative cooling loses water; closed-loop liquid and air systems recirculate it)
- A new Data Centre Designation making developers pay their own infrastructure costs rather than shifting them onto ratepayers
The Alberta Utilities Commission (the provincial electricity regulator) would take over oversight of 10 MW-plus projects; smaller ones stay with municipalities. During an electricity emergency, data centres would curtail use before households and essential services.
One carve-out: projects already permitted and well underway escape the location rules. That includes Meta's planned $13-billion AI campus in Sturgeon County, north of Edmonton, which will eventually draw about one gigawatt — 1,000 megawatts — plus a natural gas plant to feed it. In short, Alberta is tightening terms for future builds, not retroactively.
How is Ontario's approach different?
Ontario's Bill 40, the Protect Ontario by Securing Affordable Energy for Generations Act, 2025, amended the Electricity Act, 1998 to let the province decide which data centres connect to the grid at all — with criteria weighing economic development, job creation and provincial priorities.
In August 2026, the province published a proposed Economic and Strategic Assessment Framework for New Data Centres, plus a separate rate class ("Class C" in the consultation) potentially covering facilities above 1 MW. The consultation closed September 12, 2026; the enabling rules are not all in force.
The stakes are real for Northern Ontario. Data centres run 24/7 and may need new transmission lines and substations that take years to build. So the region's question: should a data centre get grid access ahead of a mine or manufacturing plant with more permanent jobs?
What has Manitoba already done?
Manitoba has gone furthest financially. Legislation receiving royal assent on June 1, 2026 amended The Manitoba Hydro Act and tax law to create separate customer classes for data centres and cryptocurrency operations, with authority for an electricity-use levy. The default levy, absent a prescribed rate, equals 100 per cent of applicable monthly energy and demand charges — effectively doubling those costs.
On October 15, 2026, Finance Minister Adrien Sala introduced further legislation to route levy revenue back to residential Hydro customers. His position: large AI and crypto facilities "should contribute fairly" and not leave ordinary customers paying for their demands. That bill remains a proposal.
Premier Wab Kinew went further in June 2026, refusing a hyperscale AI data centre near Île-des-Chênes, southeast of Winnipeg, tied to Jet.AI and Consensus Core Technologies. Developers argued the gas-fired project offered construction jobs, permanent employment and tax revenue; Kinew questioned whether the environmental and electricity footprint justified the benefits. Manitoba hasn't rejected all data centres — just the massive ones.
What comes next?
- Alberta's Bill 42 still needs passage, plus regulations to define the water rules — and those rules wouldn't necessarily cover a separate gas plant supplying a data centre
- Ontario must finalize its connection framework and decide on the Class C rate
- Manitoba's enacted pricing regime is live; the revenue-return bill awaits confirmation
The three approaches answer the same problem differently: land and water in Alberta, economic merit in Ontario, pricing power in Manitoba. All three concede the core math — AI infrastructure can demand enormous electricity while employing relatively few people post-construction.
The question is no longer whether Canada welcomes AI data centres. It's where they get built, what they contribute, and who pays.
Audit trail
- Alberta's Bill 42, introduced November 18, sets a 600-metre setback and near-zero cooling-water standard for data centres above 10 MW.
- Meta's $13-billion Sturgeon County campus would draw about 1,000 MW but is exempt as an already-permitted project.
- Manitoba's default levy equals 100% of monthly energy and demand charges for data centres and crypto operations.
- Ontario's proposed Class C rate class would cover data centres above 1 MW; consultation closed September 12, 2026.
via netnewsledger.com (Source)
More from Grace Kim
Show full bio
Staff writer covering people, launches and day-to-day practice in corporate finance and the leaders who run it at CFO Observer.
301 articles
Cross-references
- Data Centers Face 189 GW of Gas and a $140/MWh Cost Test
- Voters Rejected 52 of 53 Data Center Ballot Measures — Mississippi's Governor Says Messaging Is the Problem
- Data center power demand outgrows grid capacity tenfold
- SpaceX’s $74 Billion AI Build Faces a 6,000 MW Grid Test
- NET Power Chases AI Data Center Deal With $180M Cost Cover